1
INTRODUCTION
Background and
Context
1.1
In the Autumn of 2022, following a full public consultation
process, a Decision-Making Business Case (DMBC) was finalised by
East Sussex Healthcare Trust (ESHT) in partnership with NHS Sussex
Integrated Care Board (ICB) with the primary goal of enhancing
patient outcomes through the implementation of the proposed
cardiology transformation.
1.2
Specifically, the cardiology transformation proposal was to form
Cardiac Response Teams to support patients on their arrival at
Emergency Department (ED), alongside “hot clinics” that
will provide consultant-led rapid assessment at both of our acute
hospital sites and locate the most specialist cardiac services,
needed by a small number of patients, at Eastbourne District
General Hospital (EDGH).
1.3
The ESHT Trust Board approved the DMBC on 11 October 2022, which
was followed by the approval of the ICB at their public board
meeting on 2 November 2022.
1.4
Following NHS internal approval. The DMBC was submitted to the East
Sussex Health Overview and Scrutiny Committee (HOSC), who endorsed
the DMBC at their public meeting on 15 December 2022.
1.5
A full list of activities completed as part of the options
development and appraisal process, and the full public consultation
process, can be found in the original DMBC and published
papers.
Purpose of this paper
1.6
This aim of this paper is to provide an update to the HOSC
regarding the key actions against their recommendations made on 15
December 2022, and well as to provide additional context on the
implementation plans and activities which have been undertaken
since.
1.7
Please note, the recommendations made by the HOSC on 15 December
2022 followed on from a larger set of recommendations made by both
the ‘HOSC review Board’, and the ‘Travel and
Transport Review Group’. These recommendations were discussed
at the HOSC meeting on 15 December 2022 where a number of updates
were given, and some actions had already been implemented,
investigated and closed. The resulting list of HOSC recommendations
were therefore distilled from this larger list, and these are the
ones that are addressed directly in this paper.
2
HOSC RECOMMENDATIONS
2.2
All actions have remained under review during implementation phase
and have been discussed on a quarterly basis at the ICB Joint
Steering Board, as part of a standing agenda item on
‘Mobilisation Assurance Actions’. Following cessation
of the ICB Joint Steering Board these reverted to ESHT governance
forums as business as usual.
2.3
The HOSC meeting on 15 December 2022 reviewed this longlist of
recommendations and considered each one in turn. Some of those
actions had already been completed and closed, and some remained
open. Those actions that remained open, and were supported by the
HOSC, were distilled into a series of 4 recommendation made by the
HOSC when endorsing our proposals on 15 December 2022. An update to
each of these recommendations is provided below.
Recommendation 1
The Committee endorses the proposed
new clinical model for cardiology including:
·
Cardiology cath labs should be single sited
·
That both Eastbourne DGH and Conquest hospital sites are viable
sites
·
There is potential for new services to improve patient care and
outcomes via the ‘Front Door’ model and ‘Hot
Clinics’
·
There will be better services for patients at either Emergency
Department (ED) sites; and
·
Other services provided at each of the hospitals will not be
affected or downgraded by the proposals for cardiology.
2.4
Rather than being a recommendation that ESHT and the ICB were
required to action, recommendation 1 was an endorsement of the
clinical model proposed in the Decision-Making Business Case.
2.5
Consolidation of Primary Percutaneous Coronary Intervention (PCI),
Elective and Inpatient Cardiology activity has now been completed
at EDGH in October 2025, following an extensive estates and
construction plan. We have completed the staff consultation process
and have implemented the front door model with Cardiac Response
Team’s supporting the emergency departments (EDs).
2.6
The front door model has allowed us to start to deliver the
benefits of the model of care described during the consultation,
including the provision of improved pathways avoiding lengthy
discharge and referral processes via GPs in the community whilst
patients wait for a Cardiology outpatient appointment, and
expediting early diagnostics and treatment. This is being provided
at both sites.
2.7
Diagnostics and outpatient cardiology services continue to be
offered at both sites, so that cardiology patients have local
access to the cardiology specialty at their nearest hospital for
all cardiology care except interventional procedures and specialist
inpatient stays. Cardiology opinion, and cardiac monitoring,
remains available at both sites.
2.8
The impact of the new model of care has also meant that we have
been able to successfully recruit to long term vacant posts, which
helps reduce reliance on bank and agency, and ensure the future
sustainability of the service.
2.9
We can confirm that other services at the hospitals have not been
affected or downgraded as a result of the cardiology
transformation. Careful effort has been made throughout
implementation to ensure operational continuity throughout the
extensive programme of estates reconfiguration work.
2.10 SECAmb
have commented on the service received since the consolidation over
the past few weeks. Specifically, they have fed back how well the
model is working for receiving patients through ED, how quickly
patients have been streamed to the lab when this has been required,
and noted the good outcomes for patients so far.
2.11 We are
currently completing an initial benefits realisation project, which
will help us to understand the scale of the improvements already
made, and where we should focus our efforts next.
Recommendation 2
The Board
recommends:
·
Further measures to support the recruitment and retention of
staff are explored in collaboration with the Sussex ICS and other
system partners, which address the workforce challenges of the
service.
·
Staff recruitment and retention is monitored to ensure the
workforce challenges are being met and to assess whether additional
measures to support recruitment and retention are needed.
2.12 The
service is now fully recruited against its medical establishment
due to the transformations plans that we have implemented. This
includes recruitment to longstanding vacant consultant posts. This
has reduced reliance on bank and agency and helps to safeguard the
future of the service. It also aids in training and development for
both medical and other groups of staff.
2.13 Staffing
levels, recruitment and retention are monitored on an ongoing
basis. Measures are developed in response to the monitoring of
these metrics, and actions taken where required. The service
continues to measure workforce metrics on a rolling basis.
2.14 As a
result of the transformation programme, we have been able to meet
recommendations of the Getting It Right First Time (GIRFT) report
outlined in the DMBC in relation to the training of staff, and
improve our performance against minimum required volumes, in order
to provide a sustainable service that remains attractive to
prospective medical and non-medical cardiology workforce across all
sub-specialisms.
Recommendation 3
The Board
recommends:
3a. A package of
measures is put in place to mitigate the travel and access impacts
of the proposals on patients, families, and carers, including but
not limited to:
·
the establishment of a Travel Liaison Officer post is
essential.
2.15 The
travel liaison officer role was intended to provide a single point
of contact for patients who are experiencing difficulty in
attending their appointment or arranging hospital transport.
2.16 The
‘Travel liaison Officer’ role has since been fulfilled
by the single point of contact that is provided as part of the new
Sussex wide NEPTS contract which came into effect last year. This
role provides a single place where patients can call to discuss
their travel arrangements and difficulties and has the benefit of
being open to all hospital patients, not just those accessing
cardiology services.
·
the communication and clear messaging of advice and guidance on
travel support options, including accessing financial support,
including the ability to claim back travel costs following
appointments etc.
2.17 Since the
consultation we have updated the advice on our Trust communications
to include clearer advice on travel support and financial support
for travel costs where patients are eligible. This information is
now included on relevant patient letters, as well as being
available on our website.
2.18 The
information given has been standardised to avoid confusion, and the
same information is given by the Trust as by other sources, such as
by the new NEPTS service.
2.19 Where
patients are eligible, patients can also receive reimbursements for
travel costs whilst attending their appointment by visiting the
cashier’s office on site. Patients are informed of
eligibility criteria and told in advance what documents they will
need in order to claim back their travel expenses.
·
the provision of information on the travel support available in
referral letters via a separate leaflet or information sheet in an
accessible format and links to the website.
2.20 As above,
this information is now included on patient letters and on our
website, and accessible formats are available. This follows a
Trustwide programme to standardise and review the information on
clinic letters across the Trust, and align this with information
from other sources, such as that available online on our
website.
·
the CCG (now ICB) and ESHT explore processes to ensure patients
are asked about their travel and access needs at the point of
referral or at an appropriate point in the patient pathway.
2.21
As part of communication to patients from the Trust, it is
highlighted that patients can get in touch to raise any
difficulties they may have in attending their appointment, and
appropriate contact details are given for them to do so.
2.22
If it is a patient’s first appointment, the Trust will rely
on either 1) the patient getting in touch to let us know if they
have particular difficulties, or 2) the information being available
at the point of referral, in order for the Trust to be able to take
action to assist. It is not possible or viable for the Trust to
check personally with every new patient ahead of their first
appointment.
2.23
However, as part of raising awareness of this issue with referrers
directly, the ICB have asked referrers via identified groups (Such
as at GP forum meetings) to include any travel and access
requirements on their referrals when initially referring patients
into the Trust. The roll out of this message was monitored at the
ICB Joint Steering Board, and the message is repeated
periodically.
·
encourage providers to provide clear explanations of the
eligibility criteria for Patient Transport Services.
2.24
As explained above, eligibility criteria for patient transport
services have been recently refreshed and clarified as part of the
new NEPTS contract. This information is available online or by
phone and is aligned with the information given by the Trust.
Patients can also access the single point of contact if there is
any confusion.
·
actions to improve access via other transport alternatives (e.g.
development of a shuttle bus service, volunteer transport services,
community transport, taxi services, liaison with bus operators and
the local authority etc.).
2.25 The
travel and transport group investigated the feasibility of a
shuttle bus, however, the conclusion was that a shuttle bus would
likely not be a viable option, or serve the patients we would aim
to reach, as patients do not generally travel between hospital
sites for these appointments, but instead travel from their home
addresses.
2.26 However,
a financial viability assessment was conducted by the Trust to
determine the options available for providing a shuttle bus. In
every scenario the numbers of travellers required in order to make
the shuttle bus service a viable and justifiable use of public
funds were felt to be unachievable.
2.27
Notwithstanding the above, patients who are having difficulties in
reaching their appointment for clinical or financial reasons are
able to access NEPTS if they fall within the eligibility
criteria.
2.28 A library
of volunteer transport services was collated as part of this action
by the programme team. This was then written into the NEPTS
contract refresh in order to be maintained as part of the single
point of access requirements. This library is now maintained and
updated by the NEPTS provider.
2.29 The Trust
and the ICB met with Transport managers at ESCC to discuss the
transformation plans and potential improvements to transport links.
Despite investigating the opportunities, the local bus improvement
plan funding was not available to be used for this due to targeted
plans for where the funding was needed most. However, the transport
manager is cognisant of our plans, and a relationship is maintained
such that the Transport manager will report back on any potential
future opportunities.
Recommendation 4
The Board
recommends:
·
Implementation of the proposals is undertaken as soon as
possible, and consideration is given to mitigating the risks posed
by workforce challenges and the development of other competing
services to ensure no loss of services in the implementation
plan.
·
The Decision Making Business Case (DMBC) contains assurances
that other services provided at the two hospitals will not be
affected by the implementation of the proposals for
cardiology.
2.30 Detailed
implementation plans started to be drawn up immediately following
approval and endorsement of the DMBC. A detailed update to these
implementation plans can be found in section 3 below.
2.31 Risk
posed by workforce challenges were, and continue to be, monitored
by ESHT to ensure continuity of service. In reality, the work on
implementing the approved transformation has had an overall
positive effect on recruitment and retention which has allowed us
to better manage this risk. Certainty around the future of the
service provided by the approved model allowed us to focus targeted
recruitment for consultants, nursing and other medical
workforce.
2.32 Staff
were kept up to date with the progress of implementation, and a HR
consultation was launched as part of the implementation plan, which
has now been completed. Redeployment opportunities were explored on
an individual basis with staff where individual circumstances meant
that consolidating to Eastbourne was not a preferrable option for
them.
2.33 Further
details on the implementation can be found in section 3 of this
report, which provides a more in-depth update of the work
undertaken to date.
2.34 As per
recommendation 1, it can be confirmed that there have been no
negative impacts on the continuity or provision of other services
as a result of this transformation programme.
3
IMPLEMENTATION PROGRESS
3.1
An indicative implementation plan was developed as part of the DMBC
process, which illustrated the ambition of the cardiology
transformation plans, and provided a high-level road map for
mobilisation.
3.2
The indicative implementation timescales that were given in the
DMBC are reproduced below for reference. 
3.3
There have been some delays to the programme following development
of more detailed plans. These delays are largely due to 1) a deeper
understanding of the scope of the work required at each stage, 2)
emergent work which has been uncovered (such as plant work as part
of the moving of wards to accommodate the cardiology footprint),
and 3) difficulty with interdependencies with other estates
programmes (such as aligning with plant works and fire
compartmentation). There have also been some small-scale delays in
general procurement and construction processes.
3.4
All delays have been raised via the risk and issues process to the
ESHT Transformation Board, and the ICB Joint Steering Board, and
then later through the Operational Management Group as governance
changed. In all cases these committees have received assurance that
all mitigating actions have been taken where possible, and all
efforts have been made to minimise the impact on the timescales for
realising the benefits of the model of care for our patients.
3.5
Notwithstanding the delay in implementation outlined above, the
programme has progressed to the stage where it has been able to
realise its original proposal to 1) offer a front end cardiac
response team at both acute hospital sites, and 2) consolidate all
cardiology interventional and inpatient activity at the Eastbourne
site.
3.6
This has meant that, in October 2025 we were able to consolidate
the specialist cardiology workforce onto the Eastbourne site,
allowing us to implement the most impactful elements of our model
of care. As a result, we have already started to realise some of
the benefits outlined in the DMBC.
Implementation
Update
3.7
Following approval to proceed to implementation, more detailed
plans were drawn up, which included an estates and facilities plan,
as well as operational and workforce plans.
3.8
Implementation was planned in a phased approach in order to enable
the estates reconfigurations required to build and expand CCU,
Recovery Unit, and Cardiac Ward spaces within the footprint at
EDGH. This required a schedule of ward moves across the footprint
at EDGH in order to continue to provide other specialty services
without impacting patients or pathways.
3.9
The original high-level timescales in the DMBC indicated that the
original estimate for full implementation was by the end of March
2025. There has been a 6-month delay in implementing the proposed
model of care with respect to the consolidation of interventional
services on the EDGH site. Some of the causes of the delays to the
building and estates works required to enable us to achieve these
timescales are given below:
·
A complicated ward moves schedule was required to vacate space
identified at EDGH, this was not fully appreciated at the initial
stages.
·
The schedule of estates refurbishments has had to be adapted to
coincide with simultaneous fire compartmentation works.
·
Some ward refurbishments have revealed unexpected challenges, such
as plumbing and plant work requirements.
·
Ward moves required closing beds behind discharges, which has been
delayed by operational pressures.
·
There have been some capital reprioritisations and capital
slippages which have impacted on the programme timescales.
3.10
Notwithstanding the delays, we were able to consolidate the
interventional cardiology service at the EDGH site in October 2025
and provide the new model of care outlined in the Decision-Making
Business Case.
3.11 There is
still some further work to complete in order to fully realise all
the benefits of the Decision-Making Business Case, however, these
have not further delayed the implementation of the key advantages
of the model of care outlined in the original proposal (i.e., we
have consolidated, and are providing a front door service at both
sites).
3.12 The
remaining work required includes estates work on East Dean ward to
be completed, due January 2026. This will allow the move of the CCU
to this space, freeing up the footprint to develop the build for
the third Cath Lab outlined in the DMBC.
4.1
The new cardiology model of care outlined in the DMCB has now been
implemented, with the consolidation of Primary PCI to Eastbourne
District General Hospital occurring on 20 October 2025, and the
move of Elective and Inpatient Cardiology activity completed on 23
October 2025.
4.2
We have also fully implemented the front door model with Cardiac
Response Team’s supporting both emergency departments (EDs)
at Eastbourne District General Hospital, and the Conquest Hospital
in Hastings, which started on 20 October alongside
consolidation.
Current Improvements and
Benefits
4.3
The workforce supporting specialised interventional cardiology
procedures and inpatient stays has been consolidated from Conquest
to the Eastbourne site. (Outpatients, diagnostics and cardiac
monitoring remain available at both sites).
4.4
New rotas are in place as above which has allowed for the provision
of the front end Cardiac Response Team (CRT) model, at the Conquest
and the Eastbourne sites. Elements of the front door service has
been provided earlier during the implementation phase where it was
operationally possible to do so. With the full service being
established at both hospital sites permanently since October
2025.
4.5
New cardiology pathways are now in place enabling patients to be
seen promptly, and investigations initiated. Patients are also
brought back to a hot clinic, rather than discharged to GP. Meaning
reduced waiting times and improved access to treatment and
diagnostics across both sites. The front end model is in place on
both sites and hot clinics continue the EDGH site. CQ hot clinics
are in development, and we are using Cardiology outpatient capacity
at CQ in the interim where this is clinically indicated.
4.6
There has been an increase in MDT Working between the
subspecialities within cardiology, between different staffing
groups, including specialist nurses. Cardiology continues to have
daily touch point calls for Cardiology between the sites.
4.7
Increased supervision and improved training for medical and nursing
staff under the new model of care.
4.8
Improvement in recruitment and retention of staff. We have managed
to recruit to longstanding vacancies within the cath labs, which
includes the appointment of substantive consultants, meeting
national minimum volumes required.
4.9
Ability to recruit and retain has in turn reduced our reliance on
bank and agency staff, which reduces the cost of activity, and
improves the continuity of care for our patients.
4.10 We have
been able to meet the GIRFT recommendation to consolidate our
service and meet minimum volumes, as noted in a review of their
recommendations during a subsequent visit to the Trust in 24/25.
The transformation now allows us to continue to improve against
other GIRFT recommendations, focused on continued service delivery
development (outside of, but enabled by, this transformation).
4.11 Positive
feedback received from SECAmb, who have commented on the service
received since the consolidation over the past few weeks.
Specifically, they have fed back how well the model is working for
receiving patients through ED, how quickly patients have been
streamed to the lab when this has been required, and noted the good
outcomes for patients so far.
Benefits
Realisation Plan
4.12 Benefits
realisation is being currently being conducted following on from
consolidation onto the EDGH and can be brought back to the HOSC
once completed.
4.13 With only
one month having passed since implementation, the full benefits
realisation that was planned for Autumn 2025 has not yet been
finalised.
4.14 There are
a range of key performance indicators (KPIs) that enable us to
assess the performance of the new model of care, and an extensive
list is shown below. We will draw on these as we update our
Board.

4.15 Data
sources for national audit (such as MINAP) are not yet available
for the reason set out at 4.13. These will become available in the
coming months and will be included in the benefits realisation that
goes to our Board.
4.16 We
propose sharing the Board paper details with colleagues at HOSC to
demonstrate that the new model is functioning in a way that is both
effective from a workforce perspective and which continues to
provide quality clinical care for patients.